KULIM, Malaysia, June 1 (Bernama) — Another two key milestones have been achieved at AT&S Kulim Site as the key executives of AT&S from Austria and Malaysia celebrated the roof closing of its first production plant and the moving in of first set of tools. At the Roof Closing Ceremony, they were brought to the roof top and inked their signatures on the roof deck, followed by drilling golden bolt nuts to join two miniature roof decks on a piece of memento to commemorate the event.
At AT&S Kulim site, there are approximately 5,000 construction workers performing different construction tasks at site, 24/7, to deliver the fast track construction progress. The first crate of equipment was delivered on 27 February 2023. To-date, more than 1,400 crates of equipment have been moved into the production plant.